The list of national roads can be found at: https://www.riigiteataja.ee/akt/128062015003 from the appendix.
Harju I – Ülemiste–Soodevahe (TREV-2 Group)
The condition of the roads is good.
Road surfaces are cleaned daily with a brush. Additional maintenance and cleaning work is carried out if necessary to ensure road maintenance. On Suur-Sõjamäe Bypass, Tallinn–Lagedi Road, Nuia Street and Visase Street, the road surface and traffic control devices (traffic signs) are cleaned as needed.
The facility is served by approximately 14 tipper semi-trailers per day, and the daily transport capacity is approximately 2500-3000 tons.
The Huntaugu I sand quarry, the Väo quarry, the Väo VIII limestone quarry, and the Liivalaia VIII sand quarry are used for the supply and utilization of materials.
The following route is mainly used for transport: Kiiu–Soodla road (road no. 11105) – Tallinn–Narva highway (road no. 1) – Tallinn ring road (road no. 11) – Juhan Smuuli road (road no. 7841171) – Tallinn–Lagedi road (road no. 11290) – Suur-Sõjamäe bypass (road no. 7841235) – Nuia street (road no. 7841723) – Visase street (road no. 7841650) – Betooni street (road no. 7841162) – Paneeli street (road no. 7841160) – Tallinn–Saku road (road no. 11340) – Tallinn ring road (road no. 11).
Harju II – Soodevahe–Kangru (Verston)
The condition of the roads is good.
Sweeping tractors and a vacuum truck are in use on the roads.
Transport takes place with approximately 12 semi-trailers on the following road sections:
- Tallinn Ring Road (road no. 11, km 0–10,5)
- Tallinn–Narva highway (road no. 1, km 6–37)
- Kiiu–Soodla road (road no. 11105, km 1–4)
In addition, approximately 28 semi-trailers travel on the following road sections:
- Tallinn–Tartu highway (road no. 2, km 11,5–15,0)
- Järveküla–Jüri road (road no. 11330, km 5,6–9,5, road no. 1136 km 0.-0,8; Vaida–Urge road or road no. 11202 km 5,2-7)
Harju III – Kangru–Saku (INF Infra)
The condition of the roads is satisfactory.
State roads no. 11509 and no. 11159 are being swept.
There is mainly intra-object transport and in addition:
- On the Sutlema–Aespa–Tõdva–Viljandi Road–Kangru route with six semi-trailers.
- From the Harju 3 Saku site via the Tallinn Ring Road to the Väo quarry with three semi-trailers.
- From the Harju 3 Kangru site to the Harju 3 Saku site with four semi-trailers.
- From the Reinu limestone quarry along the Viljandi highway to the Kangru area on October 12-13.10 with two semi-trailers.
- From Männiku Betoonimeistri via Tallinn Ring Road to the Harju 3 Kangru site only 13.10 with three semi-trailers.
- From the Harju 3 Saku site along the Tallinn Ring Road to the Väo quarry with four semi-trailers.
Harju IV – Saku–Harju County/Raplamaa border (Merko & GRK)
The condition of the roads is good.
A brush machine is used to clean the roads on all these transport routes. In addition, a watering truck is planned to be used on the Männiku and Sutlema routes leading to the Kiisa emergency substation.
From October 12 to 16, 24 semi-trailer trucks are scheduled to transport construction materials each day.
- Ten trucks will move from Vää via the Tallinn Ring Road and the Tallinn–Pärnu Highway to the Kirdalu–Kiisa Road and from there via the viaduct to the site.
- Three trucks travel from the Männiku quarry along the same route every day.
- Another five trucks will travel from the Männiku quarry via the Tallinn Ring Road, Tallinn–Pärnu Highway and Tõdva–Hageri Road to the Kiisa Emergency Substation.
- Five trucks also travel from Sutlema via Tõdva–Hageri Road to the Kiisa emergency substation road per day.
- In addition, one truck per day travels from Sutlema to the site via Tõdva–Hageri Road, Tallinn–Pärnu Road, Hao Road and Soo Road.
Harju V – Soodevahe traffic interchange (TREF Nord)
The condition of the roads is good.
As needed, roads are cleaned with a brush and traffic signs and signposts are washed.
Transport takes place from the Väo Paas quarry and the Soodla II sand quarry with 10 trucks, capacity 1500 tons per day.
Rapla I – Harju County/Rapla County border – West (Verston)
The condition of the roads is satisfactory.
A brush machine operates daily on the site.
On October 12–16, material transport is planned from three locations: Reinu and Männiku quarries and Harju II section.
- Transportation from the Reinu and Männiku quarries takes place from Monday to Friday with three to four cars.
- On the same days, transports will take place from the Harju II section, from where 15 trucks will transport the material.
Rapla II – Loone–Hagudi (Verston)
The condition of the roads is satisfactory.
You will be cleaned with brush trucks with a dipping function, which are kept in constant readiness.
Transportation takes place within the facility and in addition:
- From the Künka quarry to the 2nd section with 5 trucks.
- From Reinu quarry to Loone region with 8 semi-trailers.
Rapla III – Hagudi–Alu (Tariston)
The condition of the roads is satisfactory.
Transports take place from the Hertu quarry, the Reinu III limestone quarry and the AS Silikaadi quarry.
Transports from the Hertu quarry are carried out by four semi-trailers along roads no. 15, 20141, 20131 and 20113).
INF Maavarad OÜ Reinu III limestone quarry is being transported by four semi-trailers. The transport takes place along road no. 20113 from the quarry to the Kuku viaduct.
Rapla IV – Alu–Kärpla (Verston)
The condition of the roads is satisfactory.
This week, construction materials are planned to be transported from the INF Reinu, Marina Minerals Rinnak, Maineri Sillaotsa and Verstoni Ahekõnnu quarries. Water and brush trucks will be used to clean the roads on all transport routes, if necessary. The total planned weekly transport volume is 36,000 tons.
10,000 tons of material are transported from the Reinu quarry every week, using 17 trucks. The transportation route of the Reinu quarry runs along roads no. 20113, 15, 20141, 20125 and 27.
7000 tonnes of material will be transported from the Rinnak, Sillaotsa and Ahekõnnu quarries each week. Ten trucks will be used for Rinnak and Ahekõnnu transports each week, and 12 trucks will be used for Sillaotsa transports. In addition, 5000 tonnes of material are planned to be transported from the TM_65 site in week 43.
- From the Rinnak quarry, roads no. 20160 and 27 are used, and from the TM_65 site, roads no. 20125 and 27 are used.
- Two routes are indicated in the table for transportation to the Sillaotsa quarry: along roads no. 20120, 20117, 20119, 20123, 15, 20141 and 20125 and along roads no. 20125, 20141, 15, 20143, 20145, 20117, 20128 and 20120.
- The Ahekõnnu quarry transportation route runs along roads no. 20152, 19246, 20164, 27 and 20125.
Rapla V – Kärpla–Selja (TREV-2 Group)
The condition of the roads is satisfactory.
If necessary, a brush truck is used to clean the roads.
Transportation takes place:
- From the Ahekõnnu quarry with 5-7 semi-trailers.
- From the lime quarry with 8-13 cars and 2-4 semi-trailers.
- From Reinu quarry with 10-14 cars and 18 semi-trailers.
- From Akimatsi II quarry: 8-13 semi-trailers.
- From the sand quarry: 2-4 cars and 9 semi-trailers.
Pärnu I – Selja–Tootsi (Tariston)
The condition of the roads is satisfactory.
You will be cleaned with water brush trucks and a brush tractor.
Gravel is being transported from the Ahekõnnu gravel quarry to the construction site along the main road no. 27 and the Kootja and Reichenau forest roads. 7-8 tipper semi-trailers are being used, and the estimated transport volume is 6000 tons.
There are also shipments from the Kobra quarry to the railway land on the following route: Vändra-Lokuta-Lelle road (road no. 19234) – Pärnu-Paide-Rakvere road (road no. 5) – Aluste-Kergu road (road no. 58). The volume is approximately 5000 tons per week.
Construction companies TREF Nord, Verston, Infrastructure, INF Infrastructure, TREV-2 Group, Merko & GRK Oy We use a variety of cleaning measures on a daily basis to ensure the cleanest and safest roads possible throughout the work. We also cooperate with local governments and the Estonian Transport Board in providing operational information.
What we have done and what we can still do:
- more frequent cleaning of roads;
- stricter wheel washing and cleaning procedures during field trips to sites and mines;
- separate response teams in more problematic locations;
- adjusting transport arrangements during sensitive times
Questions and contacts
For construction-related road problems, write: complaint@rbe.ee We will respond within 5 business days.
If a question or problem concerns a specific construction section, the quickest way to get information is from the relevant section's website or by contacting the builder. Information can be found by section. FROM HERE.
We thank the community for their patience and feedback. Together with our partners, we are doing everything we can to keep traffic safe and the roads as clean as possible.