The list of national roads can be found at: https://www.riigiteataja.ee/akt/128062015003 from the appendix.

Harju I – Ülemiste–Soodevahe (TREV-2 Group)

The condition of the roads is good.

Road surfaces are cleaned daily with a brush. Additional maintenance and cleaning work is carried out if necessary to ensure road maintenance. On Suur-Sõjamäe Bypass, Tallinn–Lagedi Road, Nuia Street and Visase Street, the road surface and traffic control devices (traffic signs) are cleaned as needed.

The facility is served by approximately 14 tipper semi-trailers per day, and the daily transport capacity is approximately 2500-3000 tons.
The Huntaugu I sand quarry, the Väo quarry, the Väo VIII limestone quarry, and the Liivalaia VIII sand quarry are used for the supply and utilization of materials.

The following route is mainly used for transport: Kiiu–Soodla road (road no. 11105) – Tallinn–Narva highway (road no. 1) – Tallinn ring road (road no. 11) – Juhan Smuuli road (road no. 7841171) – Tallinn–Lagedi road (road no. 11290) – Suur-Sõjamäe bypass (road no. 7841235) – Nuia street (road no. 7841723) – Visase street (road no. 7841650) – Betooni street (road no. 7841162) – Paneeli street (road no. 7841160) – Tallinn–Saku road (road no. 11340) – Tallinn ring road (road no. 11).

Harju II – Soodevahe–Kangru (Verston)

The condition of the roads is good.
Sweeping tractors and a vacuum truck are in use on the roads.

Transport takes place with approximately 12 semi-trailers on the following road sections:

  • Tallinn Ring Road (road no. 11, km 0–10,5)
  • Tallinn–Narva highway (road no. 1, km 6–37)
  • Kiiu–Soodla road (road no. 11105, km 1–4)

In addition, approximately 28 semi-trailers travel on the following road sections:

  • Tallinn–Tartu highway (road no. 2, km 11,5–15,0)
  • Järveküla–Jüri road (road no. 11330, km 5,6–9,5, road no. 1136 km 0.-0,8; Vaida–Urge road or road no. 11202 km 5,2-7)

Harju III – Kangru–Saku (INF Infra)

The condition of the roads is satisfactory.
State roads no. 11509 and no. 11159 are being swept.
There is mainly intra-object transport and in addition:

  • On the Sutlema–Aespa–Tõdva–Viljandi road–Kangru route from 28 to 30.09 September with two semi-trailers.
  • From the Harju 3 Saku site via the Tallinn Ring Road to the Väo quarry from 28.09 to 1.10 with two semi-trailers.
  • From the Harju 3 Kangru site to the Harju 3 Saku site 28.09–1.10 with four semi-trailers.
  • From Männiku Betoonimeistri via Tallinn Ring Road to the Harju 3 Kangru site on September 28–29.09 with three semi-trailers.
  • From the Harju 3 Saku site along road no. 11 to Koppelmaa 28.09–1.10 with four semi-trailers.

Harju IV – Saku–Harju County/Raplamaa border (Merko & GRK)

The condition of the roads is good.
A water bucket and brush are used to maintain roads.
Transportation takes place:

  • On the Sutlema–Tõdva–Hageri–Kirdalu–Kiisa road route, transport from the viaduct site will take place from September 28 to October 2 with four semi-trailers per day.
  • From the Männiku quarry in the direction of Hao road–Soo road, transport will take place along the Tallinn Ring Road (road no. 11) and Viljandi Highway (road no. 15). On September 28 and 29, transport will be carried out with five semi-trailers per day, and from September 30 to October 2, with four semi-trailers per day.
  • Transport from the Männiku quarry to the Kirdalu–Kiisa road viaduct site will take place via the Tallinn Ring Road and Viljandi Road. On September 28 and 29, the transport will be carried out with four semi-trailers per day, and from September 30 to October 2, with two semi-trailers per day.
  • From the Männiku quarry towards the Tõdva–Hageri–Kiisa emergency substation road, transport will take place via the Tallinn Ring Road and Viljandi Highway. On September 28 and 29, transport will be carried out with four semi-trailers per day, and from September 30 to October 2, with two semi-trailers per day.
  • Transportation from the Männiku quarry to the viaduct site on the Tõdva–Hageri–Kasemetsa–Kiisa–Saku–Tõdva route will be carried out by one semi-trailer per day from September 28 to October 2.

Harju V – Soodevahe traffic interchange (TREF Nord)

The condition of the roads is good.
As needed, roads are cleaned with a brush and traffic signs and signposts are washed.
Transport takes place from the Väo Paas quarry and the Soodla II sand quarry with 10 trucks, capacity 1500 tons per day.

Rapla I – Harju County/Rapla County border – West (Verston)

The condition of the roads is satisfactory.
A brush machine operates daily on the site.

Rapla II – Loone–Hagudi (Verston)

The condition of the roads is satisfactory.
You will be cleaned with brush trucks with a dipping function, which are kept in constant readiness.
Transport takes place within the site and additionally from the Purila quarry using 4 semi-trailers.

Rapla III – Hagudi–Alu (Tariston)

The condition of the roads is satisfactory.

Transports take place from the Hertu quarry, the Reinu III limestone quarry and the AS Silikaadi quarry.

Transports from the Hertu quarry are carried out with two semi-trailers along roads no. 15, 20141, 20131 and 20113).

INF Maavarad OÜ transports material from the Reinu III limestone quarry with four semi-trailers. The transport takes place along road no. 20113 from the quarry to the Kuku viaduct.

Soil transports are also taking place in Pärnu I section 8 with semi-trailers along road no. 20141.

Rapla IV – Alu–Kärpla (Verston)

The condition of the roads is satisfactory.
A water-brush truck is used on the Reinu quarry road if necessary. If necessary, a water-brush truck is also used on the Mainer Sillaotsa, Sokkel Sonni and Rüütja quarry roads.
Transportation takes place:

  • The INF Reinu quarry will be transported in a volume of 10,000 tons (approx. 18 cars) on route 20113 – road no. 15 (Tallinn–Rapla–Türi road)– 20141 – 20125 – Rapla–Järvakandi–Kergu road (road no. 27).
  • Trev 2 From the Reinu quarry, transports are carried out with 4 cars with a capacity of 1000 tons per week on the route 20113 – road no. 15 (Tallinn–Rapla–Türi road)– 20141 – 20125 – Rapla–Järvakandi–Kergu road (road no. 27).
  • The Verston Ahekõnnu quarry will be exported in a volume of 10,000 tons (approximately 10 cars) along the route road no. 20152-road no. 19246-road no. 20164-road no. 27-road no. 20125.
  • From Marina Minerals' Rinnak quarry with 8 trucks on route road no. 20160 – road no. 27.
  • From the Sokkel Raja quarry with 10 trucks along roads no. 20120-15-20149.

Rapla V – Kärpla–Selja (TREV-2 Group)

The condition of the roads is satisfactory.
If necessary, a brush truck is used to clean the roads.
Transportation takes place:

  • From the Ahekõnnu quarry with 10-12 semi-trailers.
  • From the lime quarry with 18-27 semi-trailers.
  • From Reinu quarry with 10-14 semi-trailers.

Pärnu I – Selja–Tootsi (Tariston)

The condition of the roads is satisfactory.
You will be cleaned with water brush trucks and a brush tractor.

Gravel is being transported from the Ahekõnnu gravel quarry to the construction site along the main road no. 27 and the Kootja and Reichenau forest roads. 7-8 tipper semi-trailers are being used, and the estimated transport volume is 8000 tons.

Transportation also takes place from the Kobra quarry to the railway land on the following route: Vändra-Lokuta-Lelle road (road no. 19234) – Pärnu-Paide-Rakvere road (road no. 5) – Aluste-Kergu road (road no. 58).

There are also transports from Rapla Section III to the Kõnnu ecoduct with 10-12 dump semi-trailers (capacity approximately 7000 tons).


Construction companies TREF Nord, Verston, Infrastructure, INF Infrastructure, TREV-2 Group, Merko & GRK Oy We use a variety of cleaning measures on a daily basis to ensure the cleanest and safest roads possible throughout the work. We also cooperate with local governments and the Estonian Transport Board in providing operational information.

What we have done and what we can still do:

  • more frequent cleaning of roads;
  • stricter wheel washing and cleaning procedures during field trips to sites and mines;
  • separate response teams in more problematic locations;
  • adjusting transport arrangements during sensitive times

Questions and contacts

For construction-related road problems, write: complaint@rbe.ee We will respond within 5 business days.

If a question or problem concerns a specific construction section, the quickest way to get information is from the relevant section's website or by contacting the builder. Information can be found by section. FROM HERE.

We thank the community for their patience and feedback. Together with our partners, we are doing everything we can to keep traffic safe and the roads as clean as possible.

How did this story make you feel?
Joyfully
0
Surprised
0
Smarter
0
Regardless
0
Sad
0
Angry
0