The list of national roads can be found at: https://www.riigiteataja.ee/akt/128062015003 from the appendix.
Harju I – Ülemiste–Soodevahe (TREV-2 Group)
The condition of the roads is good, sometimes wet from rain, sometimes dry.
Road surfaces are cleaned daily with a brush. Additional maintenance and cleaning work is carried out if necessary to ensure road maintenance. On Suur-Sõjamäe Bypass, Tallinn–Lagedi Road, Nuia Street and Visase Street, the road surface and traffic control devices (traffic signs) are cleaned as needed.
The facility is served by approximately 14 tipper semi-trailers per day, and the daily transport capacity is approximately 2500-3000 tons.
The Huntaugu I sand quarry, the Väo quarry, the Väo VIII limestone quarry, and the Liivalaia VIII sand quarry are used for the supply and utilization of materials.
The following route is mainly used for transport: Kiiu–Soodla road (road no. 11105) – Tallinn–Narva highway (road no. 1) – Tallinn ring road (road no. 11) – Juhan Smuuli road (road no. 7841171) – Tallinn–Lagedi road (road no. 11290) – Suur-Sõjamäe bypass (road no. 7841235) – Nuia street (road no. 7841723) – Visase street (road no. 7841650) – Betooni street (road no. 7841162) – Paneeli street (road no. 7841160) – Tallinn–Saku road (road no. 11340) – Tallinn ring road (road no. 11).
Harju II – Soodevahe–Kangru (Verston)
The condition of the roads is good.
Sweeping tractors and a vacuum truck are in use on the roads.
Transport takes place with approximately 5 semi-trailers on the following road sections:
- Tallinn Ring Road (road no. 11, km 0–10,5)
- Tallinn–Narva highway (road no. 1, km 6–37)
- Kiiu–Soodla road (road no. 11105, km 1–4)
In addition, approximately 27 semi-trailers travel on the following road sections:
- Tallinn–Tartu highway (road no. 2, km 11,5–15,0)
- Järveküla–Jüri road (road no. 11330, km 5,6–9,5)
Harju III – Kangru–Saku (INF Infra)
The condition of the roads is good.
National road no. 11159 and the area around the Kangru traffic junction are being swept.
There is an intra-object transport from the Kangru region to the Saku region.
In addition, transportation takes place
Harju 3 from the Kangru site via Laagri to the Väo quarry on 10–11.09 with 6 trucks.
- From Reinu limestone quarry via Viljandi road to Harju 3 Kangru site 9–11.09 with 3 trucks.
- From the Harju 3 Kangru site to the Harju 3 Saku site 7–11.09 with 2 trucks.
- From Männiku Betoonimeistri via Tallinn Ring Road to the Harju 3 Kangru site on 9–11.09 September with 2 trucks.
- From the Harju 3 Saku site along road no. 11 to Koppelmaa on 7–9.09 September with 8 trucks and on 10–11.09 September with 3 trucks.
Harju IV – Saku–Harju County/Raplamaa border (Merko & GRK)
The condition of the roads is good.
A water bucket and brush are used to maintain roads.
Transportation takes place:
7.09–11.09 transportation on the following routes:
- Sutlema–Tõdva–Hageri–Kirdalu–Kiisa road (from the viaduct to the site) with 3 trucks.
- Männiku quarry–road no. 11–road no. 15–Hao road–Soo road with 5 trucks.
- Männiku quarry–road no. 11–road no. 15–Kirdalu–Kiisa road (from the viaduct to the site) with 2 trucks.
- Männiku quarry–road no. 11–road no. 15–Tõdva–Hageri–Kiisa emergency station road with 2 trucks.
- Männiku quarry–road no. 11–road no. 15–Tõdva–Hageri–Kasemetsa–Kiisa–Saku–Tõdva (from the viaduct to the site) with 3 trucks.
- Sutlema–Kasemetsa–Kiisa–Saku–Tõdva (from the viaduct to the site) with 3 trucks.
Harju V – Soodevahe traffic interchange (TREF Nord)
The condition of the roads is good.
As needed, roads are cleaned with a brush and traffic signs and signposts are washed.
Transport takes place from the Hundaugu sand quarry with approximately 10 trucks, with a capacity of 1500 tons per day.
Rapla I – Harju County/Rapla County border – West (Verston)
The condition of the roads is satisfactory.
A brush machine with a watering function operates daily on the site. A tanker truck is used to water the gravel roads, and a vacuum truck is ordered if necessary.
Transportation takes place:
- From the Reinu quarry with 6 trucks per day.
- From the Männiku quarry with 5 trucks per day.
- From Harju II section with 6 trucks per day.
Rapla II – Loone–Hagudi (Verston)
The condition of the roads is satisfactory.
You will be cleaned with brush trucks with a dipping function, which are kept in constant readiness.
Transportation takes place within the facility and
- From Reinu quarry to section II with two semi-trailers
- 10 semi-trailers from Purila quarry to section I
- From Künka quarry to section II with 5 trucks
Rapla III – Hagudi–Alu (Tariston)
The condition of the roads is satisfactory.
Transportation takes place:
- From Hertu quarry with 6 semi-trailers along road no. 15 (Tallinn–Rapla–Türi road), road no. 20141 and 20131.
- From the Hagudi quarry with 4 semi-trailers along road no. 15 (Tallinn–Rapla–Türi road) – road no. 20113- road no. 20131.
Soil transportation also takes place along the Pärnu I section of road no. 20141.
Rapla IV – Alu–Kärpla (Verston)
The condition of the roads is satisfactory.
A water-brush truck is used on the Reinu quarry road if necessary. If necessary, a water-brush truck is also used on the Mainer Sillaotsa, Sokkel Sonni and Rüütja quarry roads.
Transportation takes place:
- The INF Reinu quarry will be transported in a volume of 10,000 tons (about 16 cars) on route 20113 – road no. 15 (Tallinn–Rapla–Türi road)– 20141 – 20125 – Rapla–Järvakandi–Kergu road (road no. 27).
- If necessary, transportation from the Estonian Limestone Lubja quarry will be carried out along the Rapla–Järvakandi–Kergu road (road no. 27).
- Trev-2 from the Reinu quarry is transported along the same roads with approximately 4 cars.
- A total of 7,000 tons (approximately 8 cars) will be transported from the Verston Rüütja quarry along the Rapla–Järvakandi–Kergu road (road no. 27).
- The Verston Ahekõnnu quarry will be exported in a volume of 10,000 tons (approximately 8 cars) along the route road no. 20152-road no. 19246-road no. 20164-road no. 27-road no.
- The removal of 300 tons of concrete from the quarry with four cars along road no. 11340-road no. 11-road no. 15 – road no. 20141-10125- Rapla-Järvakandi–Kergu road (road no. 27) – road no. 20125
- From the Rinnak quarry with 19 trucks.
Rapla V – Kärpla–Selja (TREV-2 Group)
The condition of the roads is satisfactory.
If necessary, a brush truck is used to clean the roads.
Transportation takes place:
- From the Ahekõnnu quarry with 14-17 semi-trailers.
- From the lime quarry with 15-25 semi-trailers.
- From Reinu quarry to quarry with 5-8 semi-trailers.
Pärnu I – Selja–Tootsi (Tariston)
The condition of the roads is satisfactory.
The roads are being cleaned with water-brush trucks. Water is used to control dust, and salt is also used near residential buildings on Ahekõnnu Road.
Gravel is being transported from the Ahekõnnu gravel quarry to the construction site along the main road no. 27 and the Kootja and Reichenau forest roads. The estimated transport volume is 10000 tons and 8-10 dump semi-trailers will be used.
Transportation also takes place from the Kobra quarry to the railway land on the following route: Vändra-Lokuta-Lelle road (road no. 19234) – Pärnu-Paide-Rakvere road (road no. 5) – Aluste-Kergu road (road no. 58).
Soil transportation from the Rapla III site will continue on the following routes: Seli-Koigi-Alu ree (road 20131), Rapla-Varbola road (20141), Rapla bypass (20125) – Rapla-Järvakandi-Kergu (road no. 27), Kootja road (road 2920036) and Reichenau road (road 2920039).
Construction companies TREF Nord, Verston, Infrastructure, INF Infrastructure, TREV-2 Group, Merko & GRK Oy We use a variety of cleaning measures on a daily basis to ensure the cleanest and safest roads possible throughout the work. We also cooperate with local governments and the Estonian Transport Board in providing operational information.
What we have done and what we can still do:
- more frequent cleaning of roads;
- stricter wheel washing and cleaning procedures during field trips to sites and mines;
- separate response teams in more problematic locations;
- adjusting transport arrangements during sensitive times
Questions and contacts
For construction-related road problems, write: complaint@rbe.ee We will respond within 5 business days.
If a question or problem concerns a specific construction section, the quickest way to get information is from the relevant section's website or by contacting the builder. Information can be found by section. FROM HERE.
We thank the community for their patience and feedback. Together with our partners, we are doing everything we can to keep traffic safe and the roads as clean as possible.